Client – Clark Builders
Tonnage – 1400
Erecting steel around expensive pre-existing equipment was a considerable challenge.
All lifts were made outside the footprint of the foundation walls.
Many trades were required to share the site during the erection, which added to its complexity.
The project was erected without any issues.
The contractor was extremely pleased with the final product.